Until 2025, access to the electricity grid for a photovoltaic or wind farm or a storage facility (BESS) was obtained on a “first come, first served” basis: the developer submitted the connection application (on the basis of which the network operator prepared a connection solution study), obtained the technical grid connection permit (aviz tehnic de racordare – ATR) and concluded the connection contract with the network operator. The result was a volume of ATRs far exceeding the actual capacity of the grid, many of them for projects that do not end up being built.

As of 2026, the Romanian Energy Regulatory Authority (Autoritatea Națională de Reglementare în Domeniul Energiei – “ANRE”) has changed the rules on two levels. For projects of at least 5 MW, grid capacity is allocated by auction, organised by Compania Națională de Transport al Energiei Electrice Transelectrica SA (“Transelectrica”), the transmission and system operator (TSO). For all projects above 1 MW, the guarantees required for the ATR and for the establishment authorisation have increased, and the deadlines for obtaining the building permit and the establishment authorisation have become subject to strict sanctions.

The auctions take place between 30 October and 12 November 2026 inclusive. We set out the legal framework and the consequences for developers, project buyers and lenders.

The auction procedure is governed by ANRE Order no. 53/2024 approving the Methodology on the allocation of electricity grid capacity for the connection of electricity production sites and amending and supplementing certain orders of the ANRE President in the field of connecting users to the public electricity grid, published in the Official Gazette of Romania (Monitorul Oficial), Part I, no. 758 of 2 August 2024 (“Order no. 53/2024”). The annex to the order contains the Methodology itself (the “Methodology”).

Order no. 53/2024 was amended by ANRE Order no. 79/2025, published in Official Gazette no. 1182 of 19 December 2025 (“Order no. 79/2025”). The Methodology applies from 1 January 2026, with a transitional regime and a special timetable for 2026.

In May 2026, ANRE adopted two complementary orders, both dated 21 May 2026:

  • ANRE Order no. 15/2026 amending and supplementing certain orders of the ANRE President in the field of connecting users to the public electricity grid, published in Official Gazette no. 436 of 25 May 2026 (“Order no. 15/2026”); it amends the Regulation on the connection of users to public electricity networks, approved by ANRE Order no. 59/2013 (the “Connection Regulation”), the framework connection contracts and the Methodology;
  • ANRE Order no. 16/2026 amending and supplementing the Regulation on the granting of licences and authorisations in the electricity sector, approved by ANRE Order no. 6/2025 (the “Licensing Regulation”), which introduces the guarantee for the establishment authorisation.

2. Who falls within the auction and how it works

Under Article 1 of the Methodology, the allocation of electricity grid capacity by auction concerns:

  • the connection of new electricity production sites where the installed capacity of the electricity generating installations is greater than or equal to 5 MW;
  • the granting of a power increase for export where additional electricity generating installations/storage facilities with an installed capacity greater than or equal to 5 MW are located at an existing production site/consumption and production site;
  • the connection to an existing consumption site of electricity generating installations/storage facilities with an installed capacity greater than or equal to 5 MW.

The main elements:

  • Transelectrica divides the grid into zones and publishes, for each zone and each year, the available capacity and the starting price, calculated on the basis of the estimated cost of the electricity grid reinforcement works;
  • the allocation period is 10 years and begins with the second year after the year of the auction; for the 2026 auction, the period is 2028–2037;
  • sessions are held daily, with one session taking place each working day between 8:00 and 13:00 for each year of the allocation period, in chronological order; bids may be amended or withdrawn during the session;
  • the winner concludes a capacity allocation contract with Transelectrica, provides a financial guarantee for payment of the capacity allocated by auction equal to 1% of the contract value and pays the price (calculated by multiplying the allocated capacity by the clearing price); at least 20% of the price is payable within 30 days and the full amount within 4 months of the date of conclusion of the allocation contract;
  • the issuance of the ATR for production sites of at least 5 MW is conditional on the fulfilment of all payment obligations under the allocation contract (Article 26(3¹) of the Connection Regulation).

The amounts collected are used exclusively for the development of electricity grids (Article 24 of the Methodology). The capacity price does not replace the connection tariff, which is paid separately.

3. The first auction: timetable and status as at 16 November 2026

For 2026, Order no. 79/2025 and Transelectrica’s procedure on the allocation of electricity grid capacity set a special timetable:

  • 30 June 2026: publication of the available capacity of the electricity grid;
  • 14 July 2026: deadline for submitting allocation applications and for providing the participation guarantee;
  • 24 July 2026: list of eligible participants;
  • 23 October 2026: update of the global connection solution study, including the additional works required for the development of the electricity grid;
  • 30 October 2026: first auction session;
  • 12 November 2026: last auction session.

According to Transelectrica, 12 projects with a total capacity of 491 MW registered, the participants including Romgaz and investors from Türkiye and China. Transelectrica offered 1,566 MW in 10 grid zones. The first capacities are available from 2032 in most zones, and in Dobrogea only in 2037. Auction starting prices range from approximately RON 724,000/MW to RON 3.8 million/MW, depending on the zone and the year.

The auction sessions closed on 12 November 2026. The final results (capacities allocated, clearing prices, allocation contracts) have not yet been published. The figures will need to be checked on the Transelectrica platform once the results are published.

4. Transitional regime for applications submitted before 2026

Article 7 of Order no. 53/2024, as amended by Order no. 79/2025, distinguishes between connection applications submitted before 1 January 2026 for production sites or consumption and production sites where the installed capacity of the electricity generating installations is at least 5 MW:

  • the Methodology applies to all capacity allocation applications registered with network operators from 1 January 2026;
  • applications for which the connection solution study was submitted by 31 December 2025 and the ATR was issued by 30 June 2026 continue under the previous rules;
  • amounts collected for the preparation of connection solution studies are refunded in full in the case of connection applications registered with network operators before 1 January 2026 for which the connection solution studies had not been sent by 31 December 2025.

Not sure whether your project’s ATR remains valid or whether the project must enter the auction? We review the applicable documents and deadlines.

Book a consultation

5. The new guarantees and deadlines from May 2026

ATR guarantee: 20% of the connection tariff

The financial guarantee for the issuance of the ATR rises from 5% to 20% of the connection tariff excluding VAT [Article 31(3¹) of the Connection Regulation, introduced by Order no. 15/2026]. The new amount does not apply to applications for which the operator had communicated the amount of the guarantee before the order entered into force [Article V(1)]. The increased guarantee applies to:

  • new production sites or consumption and production sites, including those with storage facilities;
  • individually connected storage facilities;
  • power increases resulting in a total approved export and/or consumption capacity exceeding 1 MW.

Deadline for obtaining the building permit and the establishment authorisation

  • the building permit and the establishment authorisation issued by ANRE must be obtained before the contract for the execution of the connection installation is concluded, but no later than 12 months after the conclusion of the connection contract and 18 months after the issuance of the ATR [Article 36(5²) of the Connection Regulation];
  • the operator may extend the deadline once only, by no more than 12 months, for justified reasons not attributable to the applicant [Article 36(5⁵)];
  • if the authorisations are not obtained in time, the ATR ceases to be valid and the connection contract terminates by operation of law [Article 36(6¹)];
  • for existing connection contracts for production sites or consumption and production sites with an approved export capacity exceeding 1 MW, the building permit and the establishment authorisation must be obtained within no more than 12 months of the entry into force of Order no. 15/2026, i.e. by 25 May 2027, subject to the same sanction [Article V(3) and (5)].

The EUR 30/kW guarantee for the establishment authorisation

Under Order no. 16/2026, the applicant for the establishment authorisation is required to provide a guarantee of EUR 30/kW, calculated by reference to the installed electrical capacity of the energy facility according to the data set out in the ATR. The guarantee, which is irrevocable and payable on ANRE’s first demand, remains valid until the signing of the acceptance report on completion of the construction works for the power plant covered by the establishment authorisation. ANRE may call it if the project is not completed within the period of validity of the establishment authorisation or if the holder abandons the project. For hybrid projects and for repowering involving an increase in installed electrical capacity, the guarantee is calculated by reference to the power increase resulting as the difference between the installed electrical capacity under the original ATR and the installed electrical capacity under the updated ATR.

ANRE’s procedure on the provision, calling and release of the guarantee was put out to public consultation in August 2026. The draft proposes exempting storage facilities added to a production site, and industry associations have asked for the guarantee for stand-alone storage to be reduced to EUR 5,000/MW. Until the procedure is adopted, the guarantee regime for BESS must be monitored closely.

Auction participation guarantee

For 2026, the participation guarantee is EUR 20,000/MW of capacity requested, at the National Bank of Romania (BNR) exchange rate on the date of issue [Article 8(4)(a) of the Methodology, as amended by Order no. 15/2026]. From 2027, the guarantee is equal to the lower of the 2026 amount and the average of the prices in the allocation contracts concluded following the previous year’s auctions, weighted by the allocated capacity.

6. What this means for developers

The new rules add to the other stages of a renewable energy investment (land, urban planning, permitting, power sale agreements) and change the order in which they must be prepared:

  • for projects of at least 5 MW, the cost of grid access becomes an auction variable and must be included in the financial model, alongside the connection tariff and the guarantees;
  • the timetable of available capacity (from 2032 in most zones) may push back the commissioning date relative to the original plan;
  • the guarantees follow one another over the life of the project and require bank guarantee facilities arranged in advance: the participation guarantee, the financial guarantee for payment of the allocated capacity of 1% of the allocation contract, the 20% guarantee on the connection tariff and the EUR 30/kW guarantee for the establishment authorisation;
  • the building permit and the establishment authorisation must be obtained within no more than 12 months of the conclusion of the connection contract and 18 months of the issuance of the ATR, which requires the land rights, endorsements (avize) and financing documents to be ready before the connection contract is concluded.

7. Due diligence for buyers and lenders

For a buyer, a valid ATR has become the most valuable asset of a project under development, but also the one most exposed to termination. When acquiring a project or providing financing, the review should cover:

  • the ATR regime: for projects of at least 5 MW, whether the project falls under the transitional regime in Article 7 of Order no. 53/2024 (dates of the connection solution study and of the ATR) or has capacity allocated under an allocation contract, with full payment evidenced;
  • deadlines: the date of the connection contract, the date of the ATR, the deadline for the building permit and the establishment authorisation, and any extensions granted by the operator;
  • guarantees: the issuer, amount, validity, beneficiary, events triggering a call and the possibility of replacement upon a change of control;
  • the establishment authorisation: the holder, the period of validity, the associated specific conditions and the EUR 30/kW guarantee;
  • transfer: whether the ATR, the connection contract, the allocation contract and the authorisation can be transferred or whether the transaction must be structured as an acquisition of shares (părți sociale) in the project company;
  • in the sale and financing agreements: conditions precedent, representations and warranties as to the validity of the ATR, price adjustment and earn-out mechanisms linked to obtaining the establishment authorisation.

For foreign investors, the acquisition may also require clearance from the Commission for the Examination of Foreign Direct Investments (CEISD), separately from the ANRE and Transelectrica procedures.

8. What you should do

  • For projects of at least 5 MW, establish whether the project has an ATR issued under the previous regime or must enter the auction, and keep evidence of the relevant dates: registration of the connection application, submission of the connection solution study for endorsement and issuance of the ATR.
  • Calculate the deadline for the building permit and the establishment authorisation: 12 months from the connection contract and 18 months from the ATR or, for existing contracts, 12 months from the entry into force of Order no. 15/2026.
  • Request the extension from the operator before the deadline expires, with documents showing that the delay is not attributable to you.
  • Monitor the results of the first auction and ANRE’s procedure on the EUR 30/kW guarantee, especially if the project includes storage facilities.

Frequently asked questions

Which projects must take part in the grid capacity allocation auction?

Projects with an installed capacity of at least 5 MW in three categories take part in the auction: new production sites; power increases for export at existing production sites or consumption and production sites, including through the addition of storage facilities; and generating or storage installations connected to existing consumption sites. The exception is applications under the transitional regime, registered before 1 January 2026, for which the connection solution study was sent for endorsement by 31 December 2025 and the ATR was issued by 30 June 2026.

How much does it cost to take part in the auction?

In 2026, the participation guarantee is EUR 20,000/MW of capacity requested. The guarantee is returned to unsuccessful bidders after the auction and to the winner after the allocation contract is signed. The winner pays the clearing price for the allocated capacity and provides a guarantee of 1% of the value of the allocation contract.

What happens if I do not obtain the building permit and the establishment authorisation in time?

If the operator has not granted an extension, the ATR ceases to be valid and the connection contract terminates by operation of law. The extension is granted once only, for a maximum of 12 months, for reasons not attributable to the applicant.

Does the EUR 30/kW guarantee also apply to batteries?

Order no. 16/2026 does not distinguish between technologies. The guarantee is provided upon applying for the establishment authorisation, and an establishment authorisation is also required for storage facilities. ANRE has proposed exempting storage facilities added to a production site, but the procedure has not been adopted as at the date of writing of this article.

Can I buy a project with an ATR issued before 2026?

Yes, but its value depends on the deadlines for obtaining the building permit and the establishment authorisation and on the guarantees provided. If the ATR ceases to be valid, a project of at least 5 MW can obtain grid capacity only by auction.

Adesman & Asociații assists developers, investors and lenders in renewable energy and storage projects, from grid connection and permitting to acquisitions and financings. You can also read our analyses of BESS projects in Romania and of due diligence for photovoltaic and BESS projects. Find out more about our energy law practice.

Preparing to take part in the capacity auction, or to acquire or finance a renewable energy project? Talk to our energy law team.

Contact us

This material is for general information purposes only and does not constitute legal advice. The applicable legal regime must be analysed in the light of the specific circumstances of each energy project and the legislation in force at the date of the analysis.